Monday, August 12, 2013

MBTA May Actually Extend to N.H.

In December of 2011 we posted a story about the history of plans to extend the MBTA's commuter rail system into the State of New Hampshire.

At the end of that post we talked about how the MBTA, NHDOT, Rockingham Planning Commission  and the towns of Plaistow and Atkinson New Hampshire were all working together to try and extend the MBTA's Haverhill Line to Plaistow. Ultimately the project was shot down by Atkinson residences in early 2012. As of last week however the plan seems to be making a comeback. 

The New Hampshire Department of Transportation says its studying alternatives for a possible extension and will be holding a public meeting on August 22nd to hear from area residents. 


When the plan was inroduced in 2011 the residents of Atkinson disliked the idea of having a layover facility in their backyard. In December of 2011, The Plaistow Area Transit Advisory Committee met for the first time in more than a decade to discuss the project. The meeting, which took place at the Atkinson Community Center, was attended by dozens of concerned Atkinson residents and local officials. The meeting eventually turned into a shouting match between residents as committee member Tim Moore tried to explain the facts of the project. According to The Eagle Tribune, the meeting got out of hand numerous times, with people shouting and interrupting each other.

Plaistow officials have been trying to bring commuter rail service to their area for years. They say that extending the commuter line would ease traffic on NH Route 125 and would help put Plaistow and the surrounding areas into metro Boston commerce. 

The first step in the project will be for the Town of Plaistow's Executive Council to pass a $658,316 feasibility study. The study will be done by HDR Engineering in Boston and will take about 18 months. The firm will do an environmental assessment of sites for a layover facility and a station platform. The study also would include estimates of the operating cost and forecast ridership.


Plaistow Town Manager Sean Fitzgerald says it is important for voters to realize the benefits of this project. “This project represents extraordinary opportunities to capitalize on existing infrastructure that would be unique to this rail project,” he said.


The public meeting will be held at Plaistow Town Hall (145 Main St) at 7pm on August 22nd. 



Saturday, December 24, 2011

Commuter Rail to New Hampshire

As most of you know the MBTA's Commuter Rail system only crosses state lines (into Rhode Island) on the south side of the system. It has been proposed for many years however, to extend some of the north side lines into the state of New Hampshire.

Before the days of MBTA.com
these pamphlets could be found for each line!
To think NH-Zone 13 was $6 1-way!
First, let me give a brief history of the MBTA trying to bring passenger rail back into the state of New Hampshire. During the 1980's the Boston and Maine Railroad (B&M) was the contractor for the MBTA Commuter Rail system (just like the MBCR today). On January 28, 1980, the B&M started an experimental service  that would run from Boston's North Station running along the Lowell line and eventually merging onto the New Hampshire main line terminating in Concord NH. It was dubbed the "Minute Man Service". This service was very popular among tourists, but it was not as popular as the B&M had first hoped it would be, resulting in federal funding being taken away and causing its demise on March 1, 1981, only a year after it first started operating.

B&M "Minute Man Service" near North Chelmsford, MA
After the Minute Man Service's early demise, it would take until 2008 for legislation to come about that might actually allow MBTA Commuter Rail to travel into NH. In July of '08 the New Hampshire Rail Transit Authority proposed a plan to extend MBTA Commuter Rail from the current Lowell terminus to Downtown Manchester, NH. The project would create nine new stops: North Chemlsford, Tyngsboro, Nashua, NH (Pheasant Lane Mall), Merrimack, NH, Manchester Regional Airport, and Downtown Manchester, NH. The plan also called for 12 to 15 round trips per day during weekdays and eight to ten round trips per day on weekends. The plan even received a total of $41 Million in Federal Grants to help fund the planning of the project. In early 2011 however, a bill was introduced into the New Hampshire legislature that would end the project's planning and give up its federal funding. Currently the project is still in limbo and, unfortunately, no one really knows what will come next.


Although the fate of this project is uncertain, another project is currently making headlines. The MBTA, NHDOT, Rockingham Planning Commision, and the Town of Plaistow New Hampshire are all working together to try and extend the MBTA's Haverhill Line from its current terminus in Downtown Haverhill to Plaistow, NH and relocate the current layover facility in Bradford to a new location on the border of Atkinson, NH. The project is currently set to cost around $25.5 Million. The projects largest obstacle however, is opposition from residents who do not want a layover facility in their area. 


The layover station has been located at Haverhill's Bradford commuter station since 1987. It is extremely small and has no room for expansion. Neighbors of the facility have complained for years that the idling trains wake them up in the early morning hours and send fumes through the open windows of homes during the summer. The new layover facility, which would be located in Atkinson, could accommodate six train sets, allowing for anticipated service expansion on the line. Like many of the MBTA's new layover facilities, when the trains are stored, they will be connected to the yard's power to allow for the train systems to run without use of power from the locomotive. The state-of-the-art energy controls and electrical systems will allow the MBTA to prohibit idling when an engine is not in active service. The facility would be owned by the NHDOT, and would be leased to the MBTA for operation.


The people of Atkinson really dislike the idea of this facility. This past Monday, December 19, 2011, The Plaistow Area Transit Advisory Committee met for the first time in more than 10 years to discuss the project. The meeting, which took place at the Atikinson Community Center, was attended by many Atkinson residents and local state officials. The meeting eventually turned into a shouting match between residents as committee member Tim Moore tried to explain the facts of the project. According to The Eagle Tribune, the meeting got out of hand numerous times, with people shouting and interrupting each other. Overall, Atkinson residents are truly showing that they do not want a layover facility in their area. 


Right now the project is still in the planning process, but they would like to have the extension open for revenue service by 2013. Hopefully Atkinson residents come onboard with the project and it can move forward as soon as possible! The next Plaistow Area Transit Advisory Committee (PATAC) will be held on February 9th. 